MARINE NOTICE No 18 of 2020
GRAND CANAL
DUBLIN

UPDATE ON PROGRAMME FOR IRISH WATER SEWER REPAIR WORKS BETWEEN LOCKS 1 & 2,
INCHICORE AREA

Further to Marine Notice 11 of 2020 Waterways Ireland wishes to advise its
users of the most recent update to the Irish Water contractor programme for
sewer repairs at Inchicore Dublin, which includes reinstatement of the Grand
Canal to navigation passage between Locks 1 & 2. 

The completion date for works is now estimated to be the end of May 2020.

The canal will remain closed to navigation until this time. As the works to
the sewer are dependent on a number of factors and are outside of Waterways
Ireland control, this date cannot yet be confirmed but updates will be
issued when available.

Waterways Ireland would like to thank our customers for their ongoing
understanding in this matter.

Patrick Harkin
Inspector of Navigation
02 March 2020